NTPC Limited said that it has commissioned 20MW out of the 56MW Kawas floating solar power project in Gujarat. The Indian state-owned power generation company said that the standalone installed and commercial capacity of NTPC is now 54.6GW. On the other hand, the installed and commercial capacity of NTPC group is 68.98GW and 68.3GW, respectively.
NTPC said that its fully-owned subsidiary NTPC Vidyut Vyapar Nigam (NVVN) has acquired a stake of 5% in Power Exchange of India Ltd (PXIL). NTPC Vidyut Vyapar Nigam has bought the stake from NSE Investment Limited, which is a co-promoter shareholder of Power Exchange of India. Power Exchange of India is said to be the […]
NTPC Limited said that Unit 4 of the 1GW Nabinagar Thermal Power Project in Aurangabad district, Bihar has entered into commercial operations. The coal-fired power station is owned by NTPC’s subsidiary — Bhartiya Rail Bijlee Company Limited. The Nabinagar Thermal Power Project has been built at Sivanpur village in Nabinagar taluk. NTPC stated: “In line […]
Inox Wind, an Indian wind energy solutions provider, has won an order for a 150MW wind farm in Gujarat from NTPC Renewable Energy Limited, a fully-owned subsidiary of NTPC. On a turnkey basis, Inox Wind will execute the wind power project at Dayapar site, Kutch District. It is slated to be commissioned by April 2023. […]
Artson Engineering Ltd has bagged a contract worth INR 11 crores from Tata Projects Limited (TPL) for the supply of fabricated structures for an NTPC project in India. The contract is to be executed within a period of five months. Based in Hyderabad, Artson Engineering is an engineering, manufacturing, and construction (EMC) contracting company. It […]
National Thermal Power Corporation (NTPC) said that it has commissioned the 15MW second phase of the 25MW Simhadri Floating Solar PV Project at Simhadri in Andhra Pradesh. Last month, NTPC had commissioned 10MW capacity of the Simhadri floating solar plant. The floating solar project has been developed on the reservoir of the 2GW Simhadri Thermal […]
Indian energy conglomerate NTPC Limited said that Unit 2 of the 1.6GW Darlipali Super Thermal Power Project in Odisha has successfully wrapped up its trial operation. As a result, the Darlipali power plant has been included in the installed capacity of NTPC, which is now 53.45GW, while that of the NTPC group is 66.87GW. The […]
Ducon Infratechnologies said that it has prevailed as the lowest bidder (L‐1) in a reverse auction for a contract held by NTPC pertaining to the Barauni Thermal Power Project, Stage II. The contract is for a flue gas desulphurization system (FGD) for the power plant located in Bihar. Stage 2 of the Barauni Thermal Power […]
Indian power utility NTPC said that it has wrapped up the trial operation of Unit 2 of the 1.32GW Tanda Super Thermal Power Station Stage-II in Uttar Pradesh. The Tanda thermal power plant, which is located in Ambedkar Nagar district, has two units, each of 660MW capacity, for its stage 2. Unit 1 of stage […]
NTPC said that it has completed the trial operation of Unit 2 of the 1.98GW Nabinagar Super Thermal Power Project in Aurangabad district, Bihar. The Nabinagar Super power project, which is operated by NTPC’s fully-owned subsidiary Nabinagar Power Generating Co. Limited, will have three units, each of 660MW capacity. NTPC has taken its total installed […]